CCR Site Services (CCR) was contracted by MSP Engineering to carry out the detailed drafting, supply and install all structural, mechanical and piping and commissioning of the Talison Lithium Plant Expansion at their Greenbushes facility.
CCR supplied and installed 500 tonnes of fabricated structural steel, various plate steel Tanks & Chutes, workshop & site fabricated piping systems as well as installation of mechanical equipment and commissioning with MSP Engineering.
To meet the tight construction timeline the structural steel was fabricated both in house at our Bunbury workshop and also by subcontracted suppliers.
All plate steel fabrication, tank and vessel fabrication and pipe spooling where competed in both of our Bunbury workshops.
Our network of subcontract providers assisted with surface treatment, rubber lining, crane support, transport and logistics including escort of wide loads.
The $12 million project was completed for MSP Engineering over a 12 month period safely, on schedule and on budget.