| INCINERATOR INSTALLATION |
|
PROJECT TYPE:
|
Project Services
|
|
CLIENT:
|
Simcoa Operations
|
|
SAFETY:
|
No incidents or accidents
|
|
VALUE:
|
Approx $1 Million
|
|
LOCATION:
|
Kemerton, Western Australia
|
|
|
|
|
|
|
Remove old vessel
|
|
|
|
|
SCOPE:
|
Removal of bracing and floor work install temporary supports to Retort Tower
Remove old vessels and redundant pipe work
Install newly fabricated incinerator vessel
Zero safety/injury incidents recorded during the shutdown with approx. 9,500 Man Hours expended
|
|
|
|
|
|
|
Installing New Duct Works
|
|
Installing New Incinerator Vessel
|
|
|
 |
 |
|